DRI能源公司完成了美国加州San Leandro 的1MW的太阳能光伏系统

来源:Solarbe.com发布时间:2010-08-25 09:31:04作者:索比太阳能

DRI 能源公司和 Mercer Foods食品风干工厂达成了一项在其食品加工厂安装1MW光伏地面安装系统的协议。

DRI Energy公司在33天内就完成了该项目,符合在截至日期之前完成的规定。

安装项目预计将会减少15%的能源用量,相当于马路上减少了217量车排出的气体。

San Leandro, CA, USA: DRI Energy Completes 1 MW Solar Photovoltaic System
DRI Energy and Mercer Foods, a company in the food drying industry have commissioned a 1 MW solar photovoltaic ground-mounted system at the Mercer Foods facility in Modesto, CA.
DRI Energy completed the project in a record 33 days, meeting a critical deadline to preserve Mercer Foodsf solar rebate from Modesto Irrigation District (MID).
The Mercer Foods installation is expected to offset almost 15% of their energy usage and provide the equivalent CO. reduction of taking 217 passenger vehicles off the road. 
"This project needed to be completed on-time or Mercer foods would not have received their reserved rebate level." said Mike Zweifel, Photovoltaic Program Coordinator at Modesto Irrigation District, "DRI Energy stepped up and made it happen."
Mercer Foods operates state of the art freeze drying equipment and is a heavy user of electricity. They have already completed extensive energy efficiency work at their plant, and solar was the next logical step. 
"We work in a very competitive industry and we are always looking for ways to run our operations more efficiently and cost-effectively," said Dave Noland, President of Mercer Foods. 


 


 

特别声明:
凡本网注明来源: "索比光伏网或索比咨询"的所有作品,均为本网站www.solarbe.com合法拥有版权或有权使用的作品,未经本网授权不得转载、摘编或利用其它方式使用上述作品。

经本网授权使用作品的,应在授权范围内使用,并注明来源: "索比光伏网或索比咨询"。违反上述声明者,本网将追究其相关法律责任。
推荐新闻
返回索比光伏网首页 回到DRI能源公司完成了美国加州San Leandro 的1MW的太阳能光伏系统上方
关闭
关闭